2.2 Data Collection Review
Data
collection and analysis for OEE is sometimes thought of as good in theory but
not in practice. The arguments against it use excuses such as "We have too
many different products" and "Our process is changed for different
style outputs." In these situations, the best approach is to step back and
review the boundaries of the system. Start where materials are input into a
systematic flow with an expected product or subassembly for the next factory
step. This transformation step is often linked with others in a series of steps
that have few if any fixed buffers. The process has an expected flow or cycle
time.
OEE
is appropriately applied to bottlenecks, critical process areas, and high
expense areas. An appropriate test is to ask, "If the effec
tiveness of this transformation step is
improved, will the bottom line be significantly impacted?’ If the answer is
yes, then putting effort into generating true OEE and driving improvement is
worthwhile.
As
an example, I once observed a work center that successfully used OEE on the
shop floor as follows. The company was highly automated; it used shop floor
computers to gather much of its information. Its Equipment Performance System
(EPS) collected not only the various downtime causes and frequencies, but also
run time and speed monitoring. From this database, the company could easily
compute OEE for each product.
Essentially,
the company picked a standard process that represented its most common product.
This product-process format was used as the benchmark for OEE. Because the
format was used so routinely, significant production history was available.
Furthermore, the product was manufactured on all of the work center’s different
equipment flowlines. Next, the work center defined how other formats and sizes
with the same product should compare with the benchmark process. This
comparison generated an OEE coefficient. The comparison was repeated for
different product families and formats as well as for different process setups.
The information gathered was valuable when communicating with superintendents and
plant managers about capability questions and the impacts of different product
mixes. It also provided the yardstick for shop floor crews to use when
examining their real time productivity on shifts.
This
plant had the advantage of having automatic data monitoring and information
feedback for nearly all the products it produced. However, at the very minimum,
plants can simply gather the information for each product run, usually manually
from cycle counters, run hour clocks and other measuring devices. Simple chart
recorders can be extremely valuable because the frequencies and duration of
events can be easily captured and analyzed.
Figure
2-1 provides a form that lists the minimum information that should be gathered.
This
information collected for each product run can quickly form the database to
begin examining OEE and to start driving productivity improvements. For
example, comparing start/stop time vs. run time measures efficiency, start/stop
cycle time vs. run time measures speed information, and units vs. transferred
output measures quality. Comparing input materials vs. units produced captures
waste and inventory information. Comments from the crew leader help
cross-functional teams work
on
root cause elimination of limiting problems. One goal is to understand the
actual functions that have failed, as well as th
e actual equipment and technical problems. Another goal is
to reconcile the actual output with the computed OEE, confirming that true OEE
is being captured.
A
decision must be made about how to handle re-work. In many processes,
manufactured items cannot be transferred or shipped with out being re-worked
first. (In such cases, the first effort of bottleneck has failed. OEE for that
manufacturing time is zero.) Re-work efforts can fall into the following three
categories.
-
The
re-work can be completed off-line using non-critical equipment. It may
even simply involve re-packaging and can be completed manually. In either
case, the rework does not impact the bottleneck system. It becomes a
manufacturing cost decision. OEE of the bottleneck does not change.
However, the measure for factory units produced should note how much
re-work was finally transferred so that reconciliation between OEE and
first pass yield can be determined.
-
The
re-work can be completed online at a time when the equipment was not
originally scheduled for production, perhaps on weekends or overtime. As
with the first category, this work essentially is completed with off-line
equipment and, again, it becomes a manufacturing cost decision. As before,
the first pass yield number needs to be identified. This type of action
should be identified when examining the TEEP metric; it involves activity on
a key asset that would have conflicted with regular production had it been
scheduled.
-
The
re-work must be completed online, competing with regular production time.
In this case, the re-work material should be looked at as new input
material. The time, speed, and quality factors should compute into the
current OEE. A note needs to be made so that the incoming inventory is
adjusted appropriately now that waste has been turned into good units.
Consider
the following example:
Assume
that 100 percent OEE (running at ideal speed with no downtime and no quality
losses) for a production area is 100 units per hour. Normal production has been
running at 75 percent OEE (75 units per hour).
During
week 1, the work area ran production for 168 hrs and produced at a normal rate
for 160 of those hours. However, during 8 of those hours, the product was
placed in the wrong colored boxes, creating 800 units of re-work. In sum, for 8
hrs, OEE is zero and for the remaining 160 hrs OEE is 75 percent. The week's
report would indicated an OEE for the area of 71.4 percent, calculated as
follows:
During
Week 2, a holiday week, the area worked 144 hours including the re-work. The
equipment ran normally. However, the 800 rework units had to be manually fed
into the system. The time for this rework took 12 hrs, resulting in only 780
good units. Because 780 units in 12 hours averages 65 units per hour, the
equivalent OEE is 65 percent for those 12 hours. The rest of the production for
the remaining 132 hrs was at a normal OEE rate of 75 percent. The week's report
would indicate be 132 hrs at 75 percent and 12 hrs at 65 percent, yielding an
OEE of 74.2 percent.
The
overall OEE for the two week period is 160 +132, or 294 hrs, at 0.75 percent, 8
hrs at 0 percent and 12 hrs at 65 percent. This yields a combined OEE of 72.7
percent.
In
general, good data collection is a key requirement for successful OEE strategy.
The success of any factory is greatly affected by how effectively accurate
information is collected and analyzed.
2.3 Practice Production Report
The
spreadsheet in figure 2-2 follows and provides a sample 40-hour production
report. It includes many different types of interruptions that illustrate the
different OEE categories. Assume this area has a normal waste rate of 3.5
percent and that it produces finished units at the rate of 4 per minute (ideal
or theoretical rate). Each column of the spreadsheet represents 10 minutes of
calendar time.
Each
event is identified with a letter and a brief description. The height of each
shaded area represents the rate at which units are being produced, with each
row representing 2 units per minute. Thus, an area 2 rows high has an expected
rate of 4 units per minute. By summing the shaded areas of production, the
number of units produced can be determined (see section 2.5). The units
produced for the experiment represented by the block following letter W are
excluded from this number.
The
analysis that follows computes OEE and TEEP for the specific 40-hour time
period in the spreadsheet. Do not confuse the production report for a weekly
report. (If the 40 hours did represent the planned production schedule for a
week, OEE would remain the same, but TEEP would be computed on the basis of 168
hours.)